Ongoing Projects:
• Construction of New Jetty (QP2) on Turnkey basis at Fotco Oil Terminal for Fauji Oil Terminal & Distribution Co. Ltd.
• Marathon has successfully completed 34 Nos Hot Tapping Project, Dia 2" - 24" on steel pipelines on at different locations all over the world.
• Zam North Rectification Works for BHP Petroleum (PTY) Ltd.
• Construction of New 16" Dia Gas Line from Engro Plant site to Mari Gas Manifold-II for Engro Fertilizers Ltd.
• Construction of 14" Effluent Piping from D2 to E1 Pond for Engro Fertilizers Ltd.
• Provision of Zam - 1 Rehabilitation Work of access road for BHP Petroleum (PTY) Ltd.
• (Effluent waste Water System) for BHP Petroleum (PTY) Ltd.
• Hot Tapping-Engro 12" DIA ON 12" steel pipeline Class 300 Hot Tapping on Natural Gas pipeline for Engro Fertilizers Ltd.
• Provision of Construction of Evaporation Ponds for BHP Petroleum (PTY) Ltd.
• Indus Highway Pipeline Crossing Protective Works for BHP Petroleum (PTY) Ltd.
• Laying of 16" dia x 0.28, w.t. API 5LX52 gas pipeline through HDD Method at Water Course Goth Ismail (In-hand) for ENGRO Fertilizers Ltd.
• Laying of 14" dia water pipeline through HDD Method at Mari Gas (In-hand) for ENGRO Fertilizers Ltd.
Client - BHP PETROLEUM (PAKISTAN) PTY LTD
Provision of laying 8" x 20KM Pipeline from Zamzama North Wellhead to Zamzama to BHP Gas Processing Plant
Client - BHP PETROLEUM (PAKISTAN) PTY LTD
Provision of laying Super Duplex 13% Crumium Special Steel Pipe 10" x 5.6KM from Zam B&D Wellheads to BHP Gas Processing Plant
Client - FOUNDATION POWER COMPANY LIMITED - DAHARKI
20" Dia Gas Pipeline for 175 MW Combined Cycle Power Plant Daharki
Client - PPL
Laying of 6" Dia High Pressure Buried Gas Pipeline from ADAM X-1 Well, Hala to SSGCL's Tie-in Point Near Goth, JORO DERO
Client - PARCO
16" Diameter MFM Pipeline crossing by HDD method at Upper Gogera Branch Canal, District Sheikhupura, Faisalabad
Client - SSGC
Installation of submerged high pressure gas pipeline under canals/crossings using HDD method at the following locations;
1) Nusrat Branch (KM 136 + 188) 24" & 20" ØP/L
2) Nara Canal (KM 39 + 57) 24" Ø P/L
3) N.W. Canal (KM122 + 917) 20" 18"Ø P/L
4) Begari Canal (KM 22 + 161) 18"Ø P/L
Client - ENI Pakistan Ltd
Pipeline and associated works for 3 years
a) Badhra 2 Gas Pipeline Laying Works (22.1km)
b) Concrete Coating and Gunniting Works on Pipeline
c) Supply of Materials for Badhra Pipeline Laying works
d) Blasting, Excavation and trenching of 24” dia Gathering line at Bhit
e) Installation of Cathodic Protection System for Badhra Pipeline
Client - PARCO
16" Diameter MFM Pipeline crossing by HDD method at Upper Gogera Branch Canal, District Sheikhupura, Faisalabad
Client - Eni Pakistan Ltd
Pipeline and associated works for 3 years
Client - Tullow Pakistan
Rainee and Fakir Wah Canal Crossings at 8" dia SARA Gas Pipeline
Client - Foundation Power Co. (Daharki) Ltd
Construction of 20" dia x 7.9mm W.T. Gas Pipeline 15KM long for 175MW, CCPP, Daharki
Pak-Arab Refinery Limited
Relocation of 20" diameter transfer line segment between Khayaban-e-Ittehad and Malir River Overhead Crossing